ANS:
•
Average Demand: the average power requirement during some specified
period of time of considerable duration is called the average demand of
installation.
• Maximum Demand: The maximum demand of an
installation is defined as the greatest of all the demand, which have
occurred during a given period. It is measured accordingly to
specifications, over a prescribed time interval during a certain period.
• Demand Factor: It is defined as the ratio of actual maximum demand made by the load to the rating of the connected load.
• Load Factor: It is defined as the ratio of the average power to the maximum demand.